Building control charges
Table A standard charges - Domestic and Residential
Proposals | Full plans Submissions (Total Fee Includes Plan and Inspection Charge. All fees are inclusive of VAT) | Building Notice Submission (All fees are inclusive of VAT) | Regularisation Submission (VAT is not chargeable.) |
---|---|---|---|
Domestic Extensions (Above Ground Level) Not exceeding 10 m2 |
£665 | £665 | £997.50 |
Domestic Extensions (Above Ground Level) Greater than 10 m2 but not exceeding 40 m2 |
£865 | £865 | £1,297.50 |
Domestic Extensions (Above Ground Level) Greater than 40 m2 but not exceeding 100 m2 |
£1,095 | £1,095 | £1,642.50 |
Domestic Extensions (Above Ground Level) Any extension greater than 100 m2 |
Individually Determined Charge - Please Contact Building Control | Individually Determined Charge - Please Contact Building Control | Individually Determined Charge - Please Contact Building Control |
Domestic Extensions (Below Ground Level) * Not exceeding 40 m2 |
£765 | £765 | £1,147.50 |
Domestic Extensions (Below Ground Level) * Greater than 40 m2 but not exceeding 100 m2 |
£995 | £995 | £1,492.50 |
Domestic Extensions (Below Ground Level) * Any extension greater than 100 m2 |
Individually Determined Charge - Please Contact Building Control | Individually Determined Charge - Please Contact Building Control | Individually Determined Charge - Please Contact Building Control |
Loft Conversions Not exceeding 40 m2 |
£725 | £725 | £1,087.50 |
Loft Conversions Greater than 40 m2 but not exceeding 100 m2 |
£875 | £875 | £1,312.50 |
Loft Conversions Any loft conversion greater than 100 m2 |
Individually Determined Charge - Please Contact Building Control | Individually Determined Charge - Please Contact Building Control | Individually Determined Charge - Please Contact Building Control |
Garages and Carports Erection of a non exempt single storey garage or carport not exceeding 100m² |
£495 | £495 | £742.50 |
Garage Conversion To form a habitable room not exceeding 40 m2 |
£525 | £525 | £787.50 |
Garage Conversion To form a habitable room not exceeding 100 m2 |
£795 | £795 | £1,192.50 |
Ancillary / Garden Buildings Erection of a single storey detached garden building or outbuilding ancillary in use to the main property not exceeding 60m² |
£725 | £725 | £1,087.50 |
Domestic Alterations ** Formation of a new bathroom or WC |
£295 | £295 | £442.50 |
Domestic Alterations ** Removal of chimney breast(s) |
£310 | £310 | £465.00 |
Domestic Alterations ** Removal or formation of an opening in a load-bearing wall |
£310 | £310 | £465.00 |
Domestic Alterations ** Re-covering a roof (per dwelling) |
£310 | £310 | £465.00 |
Domestic Alterations ** Renovation of a thermal element |
£310 | £310 | £465.00 |
Works Outside of Competent Persons Schemes Installation of replacement glazing including windows, glazed doors and rooflights (upto 10 items) |
£310 | £310 | £465.00 |
Works Outside of Competent Persons Schemes Electrical Installations (upto 12 circuits) |
£695 | £695 | £1,042.50 |
Other Domestic Works *** Total estimated cost of works not exceeding £5,000 |
£415 | £415 | £622.50 |
Other Domestic Works *** Total estimated cost of works not exceeding £10,000 |
£520 | £520 | £780.00 |
Other Domestic Works *** Total estimated cost of works not exceeding £20,000 |
£695 | £695 | £1,042.50 |
Other Domestic Works *** Total estimated cost of works not exceeding £50,000 |
£995 | £995 | £1,492.50 |
Other Domestic Works *** Total estimated cost of works not exceeding £100,000 |
£1,325 | £1,325 | £1,987.50 |
Other Domestic Works *** Total estimated cost of works exceeding £100,000 |
Individually Determined Charge - Please Contact Building Control | Individually Determined Charge - Please Contact Building Control | Individually Determined Charge - Please Contact Building Control |
Other Domestic Works *** All Other Works Not Listed Elsewhere |
Individually Determined Charge - Please Contact Building Control | Individually Determined Charge - Please Contact Building Control | Individually Determined Charge - Please Contact Building Control |
Table A- Charges and application notes
* Where a 'below ground level extension' is to be formed in conjunction with an 'above ground level extension', the below ground level extension fee will be reduced by 50% and then combined with the appropriate above ground level extension fee.
** Where additional 'domestic alterations' are to be undertaken in conjunction with other works listed elsewhere within Table A, the appropriate 'domestic alterations' fee will be reduced by 50% and then combined with the appropriate fee listed elsewhere within Table A.
*** Where 'other domestic works' (based on the cost of works) are to be undertaken in conjunction with works listed elsewhere within Table A, the appropriate 'other domestic works' fee will be reduced by 50% and then combined with the appropriate fee listed elsewhere within Table A.
Where more than one ‘above ground level extension’ is being constructed concurrently (excluding loft conversions), the total floor areas may be combined for the determination of Building Control charges. Charges are inclusive of the means of access and any other work necessary as a direct consequence of the extension/conversion.
When calculating a fee for 'other domestic works', the cost of work should exclude VAT